MT - Using BIM as a PM Tool: 4.2.7 – BIM influence on Scope

The use of BIM helped clarify project Scope to some or all stakeholders involved in at least 3 of the case studies.

Show me more...

MT - Using BIM as a PM Tool: 4.2.6 – BIM influence on Risk

The amount of positive mentions of the implementation of BIM on negative risk reduction or control reached 8, with 17.14% of the projects having more positive mentions than negative ones (Table 4.2).
Show me more...

MT - Using BIM as a PM Tool: 4.2.5 – BIM influence on Quality

Table 4.2 shows Quality as another KPI were only positive effects were perceived.
Show me more...

MT - Using BIM as a PM Tool: 4.2.4 – BIM influence on Coordination

Coordination (or Integration) Improvement was mentioned 14 times. 12 of the projects had more positive than negative mentions on Coordination due to the implementation of BIM.
Show me more...

MT - Using BIM as a PM Tool: 4.2.3 – BIM influence on Communication

The effects of BIM on communication found in all of the 35 case studies were always positive.
Show me more...

MT - Using BIM as a PM Tool: 4.2.2 – BIM influence on Time/Schedule

The second KPI with higher positive effect results of using BIM is “Time reduction or Control”. The effect of using BIM showed a positive effect on 34% of the projects (12 out of 35).

Show me more...

MT - Using BIM as a PM Tool: 4.2.1 – BIM influence on Cost

The results show clearly that the “Cost Reduction or Control” is the KPI that more often was seen as receiving a positive effect of using BIM.
Show me more...

MT - Using BIM as a PM Tool: 4.2 Findings from the Case Studies

It is important to highlight here that the approach taken to quantify the number of projects in which a KPI had positive effects was conservative in nature.
Show me more...

MT - Using BIM as a PM Tool: 4.1 Results from Case Studies

Several case studies were collected from existing literature to analyze in which areas the application of BIM had improved aspects of the projects studied.

Show me more...

MT - Using BIM as a PM Tool: 4. – Secondary Data Results and Findings

Following the methodology explained in the previous chapter, primary and secondary data needed for the research was gathered. This chapter will show the results and findings derived from the collection of secondary data.
Show me more...

MT - Using BIM as a PM Tool: 3.2.2 - Primary Data

Questionnaires were used to gather primary data. The type of primary data necessary for this research was both of quantitative and qualitative matter.
Show me more...

MT - Using BIM as a PM Tool: 3.2.1 - Secondary Data

We have already seen in previous chapters the potential benefits that BIM can bring to projects, and as a consequence, to Project Manager’s workflow. This section explains the gathering of data that proves that this potential benefits are actually materialising when BIM is being applied to real world projects.

Because of the resources and time frame available for this dissertation, it was impossible to get those results from primary data. For this reason the author chose to get the needed data from secondary sources which are easily available on the internet.

The topic of BIM has already been studied by many scholars (Aouad et. Al., 2006; Manaula, 2008; Succar, 2009; Lee, 2008); by professional groups (BSI, 2010; McGraw-Hill, 2008, 2009, 2010a and 2010b); and of course, by software vendors (Autodesk, 2007; Bentley, 2003). Of all of the above mentioned references and many others, the studies by McGraw-Hill provide a greater amount of data about the status of BIM in North America (McGraw-Hill, 2008) and in Europe (McGraw-Hill, 2010a). The latter study has its focus on UK, France and Germany. Unfortunately, no data about the status of BIM in Spain has been found, so any specific reference to this country on this research will rely for on the primary data gathered from the questionnaires that will be further explained on the following section.

Additionally to these two studies, several case studies mentioned in other papers where compiled and the data of these case studies was organized to get an overall picture of what are the real benefits that BIM is actually providing to practitioners. This data was later on compared with the a priori stated benefits of BIM (Figure 2.2 and Table 2.1) to analyze how accurate these potential benefits are and in which areas BIM is not yet being used or perceived as a useful tool. The benefits extracted from the case studies were translated into the Project Management KPI compiled in Table 3.1, to be able to quantify which KPIs benefited the most from the implementation of BIM.

All data obtained from the above mentioned secondary sources is organized and explained in Chapter 4 of this research. Links and relationships between the information gather from secondary and primary sources will be also drawn. The gathering of primary data is explained in the following section.


Show me more...

MT - Using BIM as a PM Tool: 3.2 - Data Collection

The necessary data was gathered in the following way. A combination of qualitative and quantitative data was gathered.n Primary data was gathered from questionnaires and secondary data was collected from available sources. The data was analysed to test the starting research hypothesis as part of the deductive approach, then the observations from primary data were used to formulate a theory on “How BIM can help PMs” and to propose further research topics relevant to this dissertation. The results of both the collection of primary and secondary data are explained on the Results and Findings chapter of this dissertation.

Show me more...

MT - Using BIM as a PM Tool: 3.1.2- Inductive Approach

The second part of the research question “How can BIM help Project Managers succeed in delivering complex construction projects" required a complete different approach. In this case an inductive approach was more adequate, because we were trying to come with a theory from a series of observations and from own experience. For this part, it was important to find out what were the expectations of AEC practitioners and their readiness to commit to a new technology and new processes. The opinion of construction professionals on how BIM can help AEC professionals to better deliver complex projects was also necessary.

Questionnaires (Annex I and II) were designed to gather data regarding the perception of construction professionals of BIM. These questionnaires, later explained in more detail, were the base to come up with the list of ways in which BIM can help the delivery of complex construction projects. For this part of the research both the primary data gathered from this questionnaires and the secondary data gathered from several sources were the corner stone that would allow the author to come up with a theory of how BIM can help Project Managers. At the same time, all this primary and secondary data was used to fulfil the 4 research objectives, which are here listed again.

1. To identify in which aspects is BIM implementation showing more benefits for the delivery of construction projects
2. To compare the benefits of BIM with the role of the Project Manager
3. To define which role should the Project Manager assume within the BIM framework.
4. To analyze the existing challenges for BIM implementation and estimate future developments that might mitigate these challenges.

Show me more...

MT - Using BIM as a PM Tool: 3.1.1 – Part I: Deductive approach

The research methodology begins with a deductive approach. Our initial goal was to test the hypothesis that BIM is an adequate Project Management Tool.Our first step on the process of deduction, as explained in Lancaster (2005), was to formulate the above mentioned hypothesis. There was the initial assumption that BIM is a tool for Project Management. The answer to the question “Is BIM a Project Management Tool?” was assumed to be affirmative. Nevertheless, the assumption was tested for confirmation. To do so, on Step 2 (Figure 3.1) some Key Performance Indicators [KPI] for project management were defined and on Step 3 the information was compared to these KPI to assess the relevance of BIM for PM practitioners.

The information was gathered from secondary sources. These sources are detailed later on during Chapter 4 of this dissertation (Table 4.1). Secondary data from completed construction projects that implemented BIM was gathered to analyze in which ways the projects benefited from the use of BIM. The role and influence of BIM in these construction projects was compared with the role and influence expected from a Project Manager using the KPI that were defined (Table 3.1) based on the analysis of the role of the Project Manager from the PMBOK (PMI, 2004). Although each of the PMBOK Knowledge Areas includes a lot of different aspects, they were simplified using the main topic the author considered they dealt with. This might seem as an excessive simplification, but the creation of these KPIs was essential for the deductive part of the dissertation, and the translation from a complex set of variables to easy to understand KPIs was also needed.


The Coordination KPI was created from the Integration Management PMBOK Knowledge Area. The change in name from Integration to coordination is worth explaining. The change in nomenclature from Integration to Coordination (Table 3.1) was done after reading most of the Case Studies and finding that coordination was mentioned much more than the word integration. Analyzing the content of the Integration Management chapter of the PMBOK, coordination was seen to embrace most of its meaning like “Identifying that a change needs to occur or has occurred” or “Reviewing and approving requested changes“ (PMBOK, 2004 : p.96).

It is common practice on deductive research approaches to use an extra step to the process shown on Figure 3.1 (Lancaster, 2005). This extra step is usually called falsification or discarding theory, and it is based on the premise that the researcher should aim to refute his own theory rather than to prove it (Ibid.). In this case, and despite the unorthodoxy of the chosen approach, this last step will focus on the aspects that prove the theory and not so much on those that refute it. This approach was chosen because the deductive part of our research is just a starting point for the more relevant aspect of this dissertation, the formulation of a list of aspects in which BIM can help PMs to deliver complex construction projects.



Show me more...

MT - Using BIM as a PM Tool: 3.1 – Research Philosophy and Approach

For the reasons mentioned on the previous paragraph, the overall research philosophy adopted was that of Critical Realism
The combination of the information gathered through the literature review plus the acknowledgement of the social forces affecting the study in hand make this philosophy the most adequate. (Volm, 2010).

The choice of this research philosophy is based on the fact that this research needs not to be based just on ontological or epistemological orientations, but on a combination of both as it is the case with realism (Given, 2008). We will need some empirical evidence to test that BIM is a relevant tool for the delivery of complex constructions projects, but at the same time, we want to formulate a theory of “how can BIM help” this delivery based on real world observations. This combination of orientations requires consequently a mixed research approach. The research starts with a deductive approach to test the theory and continues with an inductive approach to come up with a theory of How BIM can help PMs successfully deliver projects.


Figure 3.1 Steps followed on the deductive approach
Theory of the process of deduction (after Lancaster, 2005)





Show me more...

MT - Using BIM as a PM Tool: 3 Methodology

The author wants to proof with qualitative data that projects managed using BIM achieve better outcomes than comparable ones not using them. Factors influencing the success of projects are usually more qualitative than quantitative (Fortune and White, 2006) and that social forces have a great effect on the implementation of new technologies (Williams and Edge, 1996) and on the success of projects with complex inter-organisational structures (Maurer, 2010 and Kadefors, 2004).

Show me more...

MT - Using BIM as a PM Tool: 2.4 Chapter Summary

The literature review shows a clear tendency towards major project complexity (Chan et al., 2004; Williams, 2002; Alshawi and Ingirige, 2003). It also shows a linkage between complex projects and the existence of inter-organizational associations to accomplish these projects (Maurer, 2010).A second linkage has been drawn between inter-organizational associations and the need for “better integration, cooperation, and coordination of construction project teams” (Cicmil & Marshall 2005, cited in Maunula, 2008).

The unprecedented level of communication, collaboration and efficiency that BIM allows (Lee, 2008) seems to draw the last linkage on this chain: we have more complex projects that require inter-organizational associations; these associations require better coordination and cooperation; BIM promises to allow this increased coordination and collaboration. Ignoring BIM from the Project Management point of view seems to the author as a big mistake.

Lastly, we have seen how the industry requires a shift from a document based approach to communicating information to what many have chosen to name as Project Integrated Databases. The scholarly literature and statements from BIM supporting bodies suggest that BIM could help on this shift from documents to PIDs, for its nature is the “creation and maintenance of an integrated collaborative database of multi-dimensional information”, as we have seen in the definition of BIM on Chapter 1.

We have also seen a list of 10 potential benefits that PMs can get by implementing BIM in the projects (Table 2.1). BIM can thus be the catalyst that will enable Project Managers to reengineer the processes to better integrate the different stakeholders involved in modern construction projects.

There are and there will be challenges to the acceptance and implementation of BIM. Some of them are inherent to the new associations between stakeholders needed. The correct implementation of BIM requires “understanding and developing inter-organizational work practices” (Harty, 2005, cited in Maunula, 2008). This requirement for the implementation of BIM could be the catalyst for an overall shift towards better, more collaborative processes that could improve drastically the results and the productivity of the companies working on the AEC Industry.

The intention of this dissertation is thus to analyze the benefits of BIM as a Project Management tool and to explore in which ways and to what extent BIM will help the implementation of better processes to successfully deliver complex construction projects and which are the main challenges ahead. The methodology to achieve these goals will be explained on the following chapter.



Show me more...

MT - Using BIM as a PM Tool: 2.3.2– BIM: more than just another IOIS

The AEC Industry is based on the collaboration of several parties during the project life-cycle, and the success of projects depends on exchanging information between stakeholders on a timely manner. IOIS aim to increase the sharing of information between partners. Some years back, researchers promised that IOIS would be used “to enhance construction project documentation and control and to revolutionize the way in which a construction project team conducts business” (Nitithamyong and Skibniewski, 2004: p. 492).

Despite the benefits brought by the extensive use of IOIS, these systems are still lacking on the aspect of integration. The author has the experience of working with some of this IOIS (shared FTP portals in USA and document management systems in Germany and Spain) and they all seem to be mostly used just as online repositories of documents that all stakeholders can access. Without disregarding what the existing IOIS have accomplished – reduction of email based communication, safe storage of documents, improved communication, etc - it seems that another shift in the way things are done is needed.

BIM could be the key approach to adopt to ensure this integration and shift from the document paradigm to the Integrated Database paradigm happens. On this line of thought, the International Alliance for Interoperability [IAI] has been developing since 1995 a standard for sharing building and construction industry data. This standard has been named Industry Foundation Classes [IFC] and it follows on the work done with STEP for Product Models. Although IAI’s mission is to “support open BIM through the life cycle” (IAI, 2010a), their holistic approach to BIM encompasses many other aspects of the project delivery process. Their Information Delivery Manual [IDM] (IAI, 2010b) considers, in addition to the IFC] standards, a methodology to support the implementation of BIM, addressing the business processes and information exchange requirements.


Show me more...

MT - Using BIM as a PM Tool: 2.3.1– From documents to Project Integrated Databases

As we have seen, there is a need for better integration of project teams (Manaula 2008), one way to achieve this integration is by the proper use of Inter-Organizational Information Systems [IOIS] (Ibid.).


Figure 2.3 Use of e-business solutions in the EU industries
(adapted from e-business Watch, 2006)


“The construction and facilities industry has historically used a document-based way of working, through drawings and reports, and has communicated through ‘unstructured’ text such as letters and emails” (BSI, 2010, p. 2).

A document based way of working means that through the project life cycle there is an “unstructured stream of text or graphic entities” (BSI, 2010, p. 2). This unstructured stream is a challenge for better integrated practices. The information exchanged at the document level is generally “fuzzy, unformatted or difficult to interpret” (Ajam et. al. 2010: p. 763).

A key aspect is to understand what means “proper use” of the IOIS mentioned in the beginning of this section. Ajam et al. (2010) argue that the proper use is that of going from document sharing practices to share information at the object or element level. The proper use of these IOIS is thus the one that allows the much needed integration of project teams and the switch from the mentioned unstructured stream of entities to an integrated and interrelated use of information, what has been named by several authors as the Project Integrated Database [PID] paradigm.


Show me more...